To help us with our seed business we decided to make a large investment in our future by buying some land and building a new shed just west of our home. Looking back a few months ago it was still just an idea and today it has become reality. On August 16, materials for our new shed were delivered and since then the view from our front door looking west has changed dramatically.

Before View
After View
Let's take a step back and show a few pictures along the way.

Step 1: Drill a well
Step 2: Dirt Work
Step 3: Completed shed pad and approach
Step 4: Shed materials delivered
Step 5: Broke ground
Step 6: First wall was built
Step 7: Trusses were added.
Step 8: Metal was put on sides.
Step 9: Complete roof
Step 10: Add porch
There is still plenty to do such as pouring concrete, plumbing, electrical, finishing the office.....and the list goes on. We can't thank the Morton Builders enough for their hard work! This has been an exciting project to see come together and we look forward to the day we can start using it!